Project Redemption
Project Redemption was inaugurated with the goal of completely renovating the transmitter hall
and installing additional modern transmitters at FEBC Philippines' Bocaue International
Transmission Site.  The WWII transmitters at the site had been  operational for over 40 years,
but the signals provided were not adequate in the world of today.

Project redemption proceeded in 3 phases.  In the first phase plans were formulated, the
engineering was completed and the necessary architectural drawings were produced for all of
the works to follow.  The initial renovation of the building was begun to prepare it for the
installation of new transmitters.

In the second Phase, new transmitters were installed and brought on line.

In the 3rd Phase final cleanup works and the final run of transmission lines left over from the
SAVE project were completed
Phase I
Phase II
Phase III
Project Redemption
Reconstruction of the Bocaue International Transmission Site - Index Page